Walls are inspected for surface, cracks, pores, edges and quality of preparation for painting under agreed light conditions. Base your control on agreed standard, measurement and documentation, not just visual impression.
In brief
Walls are inspected for surface, cracks, pores, edges and quality of preparation for painting under agreed light conditions.
Base inspection on agreed standard, measurement and documentation, not solely on impression visual.
What is controlled
The "Acceptance of walls after plastering" process is used to compare the execution with the established scope and detect defects, deficiencies and risks before closing the stage.
When to check
The "Acceptance of plastered walls" inspection should be performed before covering the work, installing subsequent elements, making final payment or starting use.
Defects visible only after covering should be checked during acceptance. interstage.
Documents and conditions of receipt
Before you start, prepare: a contract, a design or established standard, product manuals, a checkpoint list, good lighting and measuring tools.
Control Tools
Typical materials and supplies: form or report, fault markers, photo documentation, manuals and data sheets.
Typical tools and equipment: spirit level or laser, staff, tape measure, flashlight or side light, camera, function tester specific to installation.
How to check
- Establish acceptance criteria based on the contract, design, instructions and agreed standard.
- Provide conditions for defects to be seen without artificial exaggeration or concealment.
- Inspect the surface visually, then perform measurements and functional tests.
- Record any discrepancies with the location, photo, meaning and expected method of repair.
- Make a decision on acceptance, conditional acceptance or refusal for a specific scope.
Conditions for reliable reception
Acceptance Carry out the "Acceptance of plastered walls" in conditions similar to those of normal use and with lighting that allows you to assess the effect without artificially hiding or exaggerating defects.
Record the measurements along with the place, tool and conditions control.
Acceptance Criteria
The inspection should be carried out in conditions suitable for subsequent use and before covering the work with another layer.
- there are no visible weld humps
- the corners are straight
- the surface is dust-free and dust-free
- the inspection refers to the agreed standard, and not solely for subjective impression
Limits of self-control
Do not perform installation tests using methods that may cause shock, flooding or damage to devices. Entrust specialist measurements to people with appropriate equipment and qualifications.
Common reception errors
- assessment only after the paint
- light set only to the extreme side without reference to the standard
- no marking of improvement points
- received in a hurry, without documents, lighting and tools measuring
Difficulty, time and risk of errors
Partial, conditional and final acceptance
The acceptance may be partial, inter-branch, final or conditional. The more elements that are covered later, the more important it is to receive them before covering them.
What to do with the check result
After receipt, sign the report or list of defects, set the deadlines and rules for re-inspection. Do not delete photo documentation until all corrections are completed.
Frequently asked questions
What does “Acceptance of plastered walls” involve?
Walls are inspected for surface, cracks, pores, edges and quality of preparation for painting under agreed light conditions. Base your inspection on agreed standard, measurement and documentation, not solely on visual impression.
What needs to be prepared before the "Acceptance of plastered walls" stage?
Before you start, prepare: a contract, a design or agreed standard, product manuals, a checkpoint list, good lighting and measurement tools.
How can you verify that “Acceptance of plastered walls” has been done properly?
Apply in conditions suitable for subsequent use and before covering the work with another layer. • there are no visible weld humps • the corners are straight • the surface is dust-free and dust-free • the inspection refers to the agreed standard and not solely to the subjective impression
When is a specialist needed for "Approval of plastered walls"?
A specialist is needed when measuring installations, tightness, structure, humidity requiring interpretation and wherever an incorrect reception may hide a technical defect.